Floor: |
¼” plate with 4” deep “V” in Center |
Paint Cond.: |
Color on request |
Floor Structure: |
12” channel outer runners and 10” channel inner runners with 3/16” plate formed angle cross members |
Walls: |
¼” plate solid-welded with “V” corrugations on 13 ½” centers. |
Roof: |
Cambered ¼” top solid-welded with 4” capped channel outside for support |
Front/Rear: |
¼” plate solid-welded with “V” corrugated steel and 45° up at rear |
Drain/Fill: |
4” suction line with valve on front of tank terminating in sump on side of tank. 8” outside manifold with 4-4” couplings with plugs and 8” frac union on ends with caps |
Gel Line: |
4” line with valve at front of tank. Line will be 45° up at rear. |
Man ways: |
20” man ways front and curbside rear. Three non-sealing hatches on roof with safety bars |
Tow Latching: |
Standard 5th wheel kingpin |
Welds: |
All welds continuous including substructure and cross members. |
Axle/ Wheels: |
22,500# axle with DOT approved braking system and new 11.0 x 22.5 tires on steel wheels. |
Access: |
Front stairway with handrails. |
Finish: |
Interior- blasted and coated with epoxy liner; Exterior –blasted, primed and top coated with polyurethane paint; Floor substructure-undercoated with coal tar epoxy |
Testing: |
Full capacity static water test |
Dimensions : |
Overall-45’2” long, 8’6” wide, 9’ 10” tall to top of roof rafters. Capacity – 500bbl |